Bretts Aggregates will recommence piling works at East Quay, Newhaven Harbour for the Process Plant and Rail Foundations in the week commencing 7th October.

There will be 1 rig working initially for the first week with a second being brought in for the remaining works.

The works are estimated to complete within 5 weeks. [8th November].

Bretts will  be monitoring these activities, as before, to ensure they are working to the requisite noise levels contained in planning permission conditions.