Dear Local Resident,

As you may be aware the construction of the new port access road is progressing well. We are soon to achieve a large project mile stone with the first deliveries of the steel beams for the bridge. These are being fabricated in Darlington and will soon start setting off on their 3 day journey to us here in Newhaven.

The largest of the beams is just short of 50m long and with the transport vehicle will be approximately 60m in length. This is equivalent to 6 London double decker busses.

There are 9 beams and these are being delivered in groups of 3. Due to their size they are being transported under an Abnormal Load Movement Order and will have a police escort. The time of the movement is dictated to us by the local authorities and written into the Order.

The first beams are due to transit through East Sussex on Wednesday 13th November arriving in Newhaven between 12:00hrs and 14:00hrs. During this time delays are to be expected as the beams manoeuvre through the local road systems.

Residents of Beach Road are especially requested not to park on the road between these hours on the dates below, where the destination is East Quay, to avoid issues with the beams transiting to the port.

Beam Delivery

Time into Newhaven

Date

Destination

1

12:00-14:00

13th November 2019



East Quay, Newhaven Port

 

2

12:00-14:00

14th November 2019



East Quay, Newhaven Port

 

3

12:00-14:00

15th November 2019

East Quay, Newhaven Port

 

4

12:00-14:00

4th December 2019


McKinley Way, Newhaven

 

5

12:00-14:00

5th December 2019



McKinley Way, Newhaven

 

6

12:00-14:00

6th December 2019



McKinley Way, Newhaven

 

7

12:00-14:00

05th February 2020

East Quay, Newhaven Port

8

12:00-14:00

06th February 2020



East Quay, Newhaven Port

 

9

12:00-14:00

07th February 2020

East Quay, Newhaven Port

For further information on the scheme please refer to the following:

Visit: eastsussex.gov.uk/Newhaven-port-access-road

Email: newhavenpar@bamnuttall.co.uk

Phone: 01651 267007

Site notice boards





 

nat maritime

nat maritime

Contact Us | Site Map | Third Party Privacy Notice

The material on our site is given for general information only, and does not constitute professional advice. You should take specific advice before taking a course of action as we do not accept directly or indirectly any responsibility or liability for loss arising from information on this site. The site includes links to other sites which we consider may be of interest to you but we will not be liable for their content. Users linking to other sites do so at their own risk and according to the terms and conditions of those sites. We cannot guarantee that the site and any downloads reach you virus free and you are responsible for taking any appropriate anti-virus precautions for your own safety and peace of mind. All use of the Port is subject to Newhaven Port & Properties Ltd terms & Conditions which can be viewed here .

Copyright © Newhaven Port & Properties Ltd.
All rights reserved East Quay, Newhaven, East Sussex, BN9 0BN, United Kingdom